ajk1
Structural
- Apr 22, 2011
- 1,791
Given:
Existing 2 span post-tensioned (p.t.) garage floor beams with corroding unbonded tendons in the old push-thru sheaths, about 35 years old.
Can not reliably replace the tendons because of various reasons (such as the "pinching effect" where transvers p.t. girders cross, criss-crossing of tendons in the beam, etc. We tried over the years!
Required:
Assume all the existing p.t. eventually fails.
Question:
Can externally installed Dywidg straight bars, 2 near the top of each 2-span beam (just below the slab soffit) and 2 near the bottom of each beam (just above the beam soffit) that are then prestressed to apply the same magnitude of exial force as the existing p.t. in the tendons, be acceptable, if calculations show that the new Dywidag bars apply enough force to keep the entire T-beam section (slab and beam) in compression?
Existing 2 span post-tensioned (p.t.) garage floor beams with corroding unbonded tendons in the old push-thru sheaths, about 35 years old.
Can not reliably replace the tendons because of various reasons (such as the "pinching effect" where transvers p.t. girders cross, criss-crossing of tendons in the beam, etc. We tried over the years!
Required:
Assume all the existing p.t. eventually fails.
Question:
Can externally installed Dywidg straight bars, 2 near the top of each 2-span beam (just below the slab soffit) and 2 near the bottom of each beam (just above the beam soffit) that are then prestressed to apply the same magnitude of exial force as the existing p.t. in the tendons, be acceptable, if calculations show that the new Dywidag bars apply enough force to keep the entire T-beam section (slab and beam) in compression?