Welding community members,
I was told that CS 2"sch std groove weld joint with manual GTAW could be done at 6 minutes. Based in my experience that I have with process It could be done at minimum 15 minutes to 20 minutes. This include positioning, tack weld and welding in 2GR position.
How much do you perform sich weld no matter how are the wire diameter and the number of passes ?
I appreciate any contribution.
EWE