Apr 8, 2013 #1 Odd01 Materials Joined Jan 31, 2013 Messages 10 Location NO Hi, Is there someone that know where to find in ASME standard where it is mention holding time after welding before NDT can be carry out(example 24h after welding). Tanks, Odd01
Hi, Is there someone that know where to find in ASME standard where it is mention holding time after welding before NDT can be carry out(example 24h after welding). Tanks, Odd01
Apr 8, 2013 #2 stanweld Materials Joined May 9, 2003 Messages 2,906 Location US Such time limits are not defined. Upvote 0 Downvote
Apr 10, 2013 #3 OGMetEngr Materials Joined Oct 14, 2012 Messages 150 Location US Not sure on ASME, but AWS D1.1 C6.11 specifies 48h after welding for high strength QT steels (ASTM A514, A517). NORSOK has a similar requirement. Upvote 0 Downvote
Not sure on ASME, but AWS D1.1 C6.11 specifies 48h after welding for high strength QT steels (ASTM A514, A517). NORSOK has a similar requirement.
Apr 11, 2013 Thread starter #4 Odd01 Materials Joined Jan 31, 2013 Messages 10 Location NO Thanks for information. Odd01 Upvote 0 Downvote