Jan 4, 2011 #1 fakhfakh Industrial Joined Nov 11, 2004 Messages 48 Location TN Hello, Is there any paragraph in PD 5500 requiring to wait a lapse of time (12h or more) after weld completion in order to start NDT (UT, RT,...) ? Thanks
Hello, Is there any paragraph in PD 5500 requiring to wait a lapse of time (12h or more) after weld completion in order to start NDT (UT, RT,...) ? Thanks
Jan 10, 2011 Thread starter #3 fakhfakh Industrial Joined Nov 11, 2004 Messages 48 Location TN Thanks Upvote 0 Downvote
Jan 10, 2011 #4 ndeguy Industrial Joined Oct 13, 2005 Messages 220 Location TR You are welcome Upvote 0 Downvote