HeavyCivil
Structural
- Aug 5, 2009
- 184
Hi,
I am designing a very large septic tank (or series of tanks) for a small-town WWTP. I have reinforced the 8" walls based on PCA moment tables keeping steel stress at or bellow allowable per ACI 350 10.6.4.2. So, I am not too worried about cracking in the walls. The slab is a different story.
Most tanks I have done have had Mat foundations. This site, however, has good soil and to keep cost down by saving concrete and an the extra layer of bar, I would like to use a slab for the tank bottom which is poured continuously with wall ftg's (ftg's were sized like retaining walls, resisting overturning and sliding so slab would not be subjected to any compression.
Obviously it is very important to keep crack widths to very very small widths. I was planning on using a 6" slab with #4's each way @8".
I was not planning on using control joints, mostly because I do not understand them in function enough to be sure that I won't be causing cracks larger than desirable. I am hoping that using that much steel (Rho=.004) and designing a good mix will eliminate undesirably large cracks and the need for control joints.
Is this an accurate method for achieving the water-tight goal??
I am designing a very large septic tank (or series of tanks) for a small-town WWTP. I have reinforced the 8" walls based on PCA moment tables keeping steel stress at or bellow allowable per ACI 350 10.6.4.2. So, I am not too worried about cracking in the walls. The slab is a different story.
Most tanks I have done have had Mat foundations. This site, however, has good soil and to keep cost down by saving concrete and an the extra layer of bar, I would like to use a slab for the tank bottom which is poured continuously with wall ftg's (ftg's were sized like retaining walls, resisting overturning and sliding so slab would not be subjected to any compression.
Obviously it is very important to keep crack widths to very very small widths. I was planning on using a 6" slab with #4's each way @8".
I was not planning on using control joints, mostly because I do not understand them in function enough to be sure that I won't be causing cracks larger than desirable. I am hoping that using that much steel (Rho=.004) and designing a good mix will eliminate undesirably large cracks and the need for control joints.
Is this an accurate method for achieving the water-tight goal??