A contractor built a sidewalk with cross slopes of up to 5.7%, instead of 2% max. Rather than make him rip out and replace the affected sections, could bonded white-topping work? It's mostly offset from the road, so curb height isn't a factor in most places.
What items would need attention? I'm assuming some surface preparation would be needed, and control joints need to coincide. If the minimum thickness is over 1/4"(6mm), panels would need to be replaced to transition to existing surfaces to remain. Anything else?
What items would need attention? I'm assuming some surface preparation would be needed, and control joints need to coincide. If the minimum thickness is over 1/4"(6mm), panels would need to be replaced to transition to existing surfaces to remain. Anything else?