pattimelt
Industrial
- May 12, 2010
- 40
Another individual was talking about how in the course of his carreer (military & government connected) he had always had any welds involving moment connections UT. This got me thinking-I have a number of these connections in one of our structures, and had only done the VT. I have looked at the drawings that were issued for construction, and no notes from the P.E. AWS D1.8 is not a stand alone code, and it is not referenced in my scope. What say you all - is this a D1.1 requirement or is this something I can file as good to know for the next one?