Attached is a screen shot of a drawing I'm being asked to approve.
One hole has been assigned as Datum A. Several holes' 2D positions are dimensioned from it, each with a simple ± tolerance.
No dimensions use "feature control frames" , so there are no dimensions with specific references to Datum A. True position etc.
Is it necessary to assign a datum ?
Is it "wrong" to assign a datum ?
thanks,
Dan T
One hole has been assigned as Datum A. Several holes' 2D positions are dimensioned from it, each with a simple ± tolerance.
No dimensions use "feature control frames" , so there are no dimensions with specific references to Datum A. True position etc.
Is it necessary to assign a datum ?
Is it "wrong" to assign a datum ?
thanks,
Dan T