I recently was on a bridge project where the bridge was completed in two phases. The bridge used inverted t beams and spans were 50’ long. The construction joint was not on center line of bridge but the last beam before. After pouring the 6” deck on the second phase you could see that the first beam by the construction joint had more camber left in it than all of the other beams. What effect will this have on the bridge.