Good welders will build the required weld by placing short pieces at intervals and then returning to fill in the gaps, (this keeps the distortion due to heating a localized area to a minimum.) I would use two fillet welds, one on plate overhang to far edge of flange and one at start of cantilever of plate to other side of flange.