jike,
he means "top down construction" this is where you construct basements from ground level down. First you construct diaphragm walls and bored piles, then you excavate. When you reach the level of the first basement level floor you cast the slab, this struts the diaphragm walls. Then you lift an excavator through a hole in the cast floor slab to excavate for the next level down. Work continues until you reach the lowest level.
There are advantages, in particular that no struts, or at least reduced strutting is required. Disadvantages include the need to provide ventilation for the diesel engined excavators and of course spoil removal is slow by crane and skip.