Jan 26, 2019 #1 mechengineer Mechanical Joined Apr 19, 2001 Messages 268 Location SG If the governing MAWP for whole preaaure vessel in Compresse claculation report has been used in the design of nozzle loads (WRC 107 or 297) and support system (skirt or saddle supp.)?
If the governing MAWP for whole preaaure vessel in Compresse claculation report has been used in the design of nozzle loads (WRC 107 or 297) and support system (skirt or saddle supp.)?