carmoch
Geotechnical
- Feb 16, 2007
- 14
Hi, I have a problem. We have to propose a solution in a area which is gained to the sea. There is a sector which is constructed 4 oil/water tanks (with a load of 1,2 and 2 kg/cm2, respectily).
The fill is composed of gravel and sand (USCS, GP-GM or GW-GP),mainly. It has a average thickness of 22 m, and have found areas with gaps due to poor compaction (less than 1 m).and the natural substrate is formed of sands (Nspt between 12 and 40).
Initially I suggested an improvement of the land with the construction of piles to natural terrain, but I think it could pose a foundation by micropiles and / or jet grouting (filling the gaps with injections of compensation). This treatment may leave the field or the field should always take natural?
On the other hand, I have other structures with the lowest load (0.4 to 0.7kg/cm2). Could raise a replacement ground only? Do you suggest?
Thank you very much.
The fill is composed of gravel and sand (USCS, GP-GM or GW-GP),mainly. It has a average thickness of 22 m, and have found areas with gaps due to poor compaction (less than 1 m).and the natural substrate is formed of sands (Nspt between 12 and 40).
Initially I suggested an improvement of the land with the construction of piles to natural terrain, but I think it could pose a foundation by micropiles and / or jet grouting (filling the gaps with injections of compensation). This treatment may leave the field or the field should always take natural?
On the other hand, I have other structures with the lowest load (0.4 to 0.7kg/cm2). Could raise a replacement ground only? Do you suggest?
Thank you very much.