1SEngineer
Structural
- Aug 27, 2007
- 37
Subject: Preliminary Research
Problem: There is a sewer pipe drainage problem in a two story condo. The condo hired a plumber to investigate the problem, and he believes the only solution is to remove and replace the sewer pipe. The plumber wants to create a tunnel(3'x3') below the slab to install the new sewer pipe (3" diameter).
Structure: We don't have much info yet about the structure but we are fairly certain that the building has the following components: shallow foundations, possibly spread or monolithic footings, 4" slab on grade, bearing walls are reinforced masonry.
Possible Solutions:
1. No tunneling allowed. The plumber has to saw cut the slab from above and all plumbing work will have to take place from the upper side od the slab. In order to do this, (3) condo units will have to be torn apart. Kitchen, Bathroom, Flooring, Etc. Estimated cost is $125K.
2. Tunnel underneath the shallow foundations and slab on grade. Estimated cost is $25K. The tunnel would be 3'x3' approximatley. I believe this is very feasable but of course there is always the risk of some settlement and cracking to occur in the slab and masonry and the development of additional stresses in these materials. If this route is taken, preliminary considerations would be to excavate in small lengths and widths and intall P.T. 4x4 or steel tube shoring as the excavation progresses, perhaps 4' on center. Arching action in the bearing walls will assist somewhat, but shoring would still be place underneath these footings.
I am a bit uncertain regarding backfilling as there is no way that this can be done and the bearing capacity maintained. I have thought about using flowable fill but I'm not sure if this will provide adequate bearing capacity due to voids. And it creates other problems if the pipe needs to accessed again.
I am curious to know how others on the forum would approach this challenge.
Thanks!
Problem: There is a sewer pipe drainage problem in a two story condo. The condo hired a plumber to investigate the problem, and he believes the only solution is to remove and replace the sewer pipe. The plumber wants to create a tunnel(3'x3') below the slab to install the new sewer pipe (3" diameter).
Structure: We don't have much info yet about the structure but we are fairly certain that the building has the following components: shallow foundations, possibly spread or monolithic footings, 4" slab on grade, bearing walls are reinforced masonry.
Possible Solutions:
1. No tunneling allowed. The plumber has to saw cut the slab from above and all plumbing work will have to take place from the upper side od the slab. In order to do this, (3) condo units will have to be torn apart. Kitchen, Bathroom, Flooring, Etc. Estimated cost is $125K.
2. Tunnel underneath the shallow foundations and slab on grade. Estimated cost is $25K. The tunnel would be 3'x3' approximatley. I believe this is very feasable but of course there is always the risk of some settlement and cracking to occur in the slab and masonry and the development of additional stresses in these materials. If this route is taken, preliminary considerations would be to excavate in small lengths and widths and intall P.T. 4x4 or steel tube shoring as the excavation progresses, perhaps 4' on center. Arching action in the bearing walls will assist somewhat, but shoring would still be place underneath these footings.
I am a bit uncertain regarding backfilling as there is no way that this can be done and the bearing capacity maintained. I have thought about using flowable fill but I'm not sure if this will provide adequate bearing capacity due to voids. And it creates other problems if the pipe needs to accessed again.
I am curious to know how others on the forum would approach this challenge.
Thanks!