Dik, have you checked any analyses with that. I don't have too much problem with two cycles when the loads are not too different, most of the cases like that, most of the distribution is done in two cycles.
What does bother me is that there is no sidesway, the example has a reaction at the right end of the rightmost beam so it is not a problem there. This would really worry me in a multi-story bldg.
I think I'll play with this when I get a chance. I'll be using full MD but run it on a spreadsheet, once it is blocked out it is very fast.
I wonder how they attack lateral load cases, I used to put hinges in the columns, halfway between the floors, to get a quick and dirty estimates.
Michael.
Timing has a lot to do with the outcome of a rain dance.