Ron247
Structural
- Jan 18, 2019
- 1,151
I am trying to get some assistance about how much “overage” do concrete estimators add to their concrete quantities for different types of concrete work (slabs, footings, walls etc.). I have never found any good reference on the subject. I made some estimations of my own years ago based on common problems encountered in construction. I have seen general statements like 5% to 10% as general numbers but I can easily see many examples where these can either be conservative or unconservative.
For me, the harder ones are casting against soil such as footings or slabs on grade. Formed items such as columns, walls and beams have fairly exact dimensions while casting against soil is not so easily controlled. 5% seems reasonable for columns, walls and beams and I tend to use 7%-10% for elevated slabs.
The problems I tend to see with casting against soil are:
[ul]
[li]Measuring, marking and excavating a theoretical straight line that is the width of a string in theory; the paint or chalk used is 1” to 2” wide in reality; just adding 2” to a 20” width is 10%[/li]
[li]Footing widths that do not match somewhat standard backhoe/excavator bucket widths; can easily wind up with footings 2” to 3” wider than specified; as the footing gets wider, this becomes less of any issue[/li]
[li]Soil that sloughs off easily[/li]
[li]Having to use 2” mudsills on foundation excavations due to rain; when the backhoe bucket has 3” teeth, you tend to get 3” mudsills instead of 2”[/li]
[li]Slabs on Grade subjected to rain during fast-track jobs that tend to make contractors muck out the wet stuff but not spend time placing stone, just pour the concrete thicker or pour a mudsill over the entire area (really hard to allow for)[/li]
[li]slab thickness inconsistent due to poor grading; adding 1/2" to a 4" slab is 13%[/li]
[li]Other[/li]
[/ul]
Any info would be appreciated. At this time I am not looking so much at the size of the project although that also affects the number.
For me, the harder ones are casting against soil such as footings or slabs on grade. Formed items such as columns, walls and beams have fairly exact dimensions while casting against soil is not so easily controlled. 5% seems reasonable for columns, walls and beams and I tend to use 7%-10% for elevated slabs.
The problems I tend to see with casting against soil are:
[ul]
[li]Measuring, marking and excavating a theoretical straight line that is the width of a string in theory; the paint or chalk used is 1” to 2” wide in reality; just adding 2” to a 20” width is 10%[/li]
[li]Footing widths that do not match somewhat standard backhoe/excavator bucket widths; can easily wind up with footings 2” to 3” wider than specified; as the footing gets wider, this becomes less of any issue[/li]
[li]Soil that sloughs off easily[/li]
[li]Having to use 2” mudsills on foundation excavations due to rain; when the backhoe bucket has 3” teeth, you tend to get 3” mudsills instead of 2”[/li]
[li]Slabs on Grade subjected to rain during fast-track jobs that tend to make contractors muck out the wet stuff but not spend time placing stone, just pour the concrete thicker or pour a mudsill over the entire area (really hard to allow for)[/li]
[li]slab thickness inconsistent due to poor grading; adding 1/2" to a 4" slab is 13%[/li]
[li]Other[/li]
[/ul]
Any info would be appreciated. At this time I am not looking so much at the size of the project although that also affects the number.