hi,
in our project we have api 5l x65 cladded with 3mm inconel
625 the thk of carbon steel portion is more than 19mm in this case pwht is require or not.
regards
r.salimi
in our project we have api 5l x65 cladded with 3mm inconel
625 the thk of carbon steel portion is more than 19mm in this case pwht is require or not.
regards
r.salimi