TheDruid
Chemical
- Oct 22, 2007
- 14
Hi folks,
we have the following problem:
existing tank has inlet line DN65 with a CV. Before this CV there is saturated steam with 22 bar@theoretical 14 t/h. The tank is designed for 12 bar.
We are designing now the PSV for the tank. Failure case is broken CV.
regarding the inlet pressure drop, is it correct, that only the part from tank to PSV is important (and not the line from boiler to tank to PSV) ?
Are there any regulations about the flow rate. 14 t/h is the theoretical flow rate of the boiler (which is approx. 150 m away, with several bends and valves --> pressure drop). Could this be a problem, regarding vibrations ?
For our calculations we get a DN65 valve (14.5 t/h).
Is this the correct choice ?
thanks very much &
best regards
Alex.
we have the following problem:
existing tank has inlet line DN65 with a CV. Before this CV there is saturated steam with 22 bar@theoretical 14 t/h. The tank is designed for 12 bar.
We are designing now the PSV for the tank. Failure case is broken CV.
regarding the inlet pressure drop, is it correct, that only the part from tank to PSV is important (and not the line from boiler to tank to PSV) ?
Are there any regulations about the flow rate. 14 t/h is the theoretical flow rate of the boiler (which is approx. 150 m away, with several bends and valves --> pressure drop). Could this be a problem, regarding vibrations ?
For our calculations we get a DN65 valve (14.5 t/h).
Is this the correct choice ?
thanks very much &
best regards
Alex.