Thank you for you reply.
Now what's the problem is general contractor hired us to design the plant piping system. The plant's engineer and us both agree to use galvanized steel pipe. But the general contractor ordered black steel, which is wrong, then he suggested PVC. He talked to the plant engineer,and told him PVC is low cost, and let us to support him. We understand PVC has more chance of breakage which will cause whole plant shut down.