zmm1
Industrial
- Mar 14, 2011
- 11
Well its one mess onto the next. The owners have a plan to install a mazak space gear in a large offsite building in a rural area. The area has a REA electric system with their very expensive load demand fees. While the building has a 45KVA 208 service its nowhere near large enough.
The proposed plan is to install a 125 KVA onan generator on site to power the laser. I have suggested at a minimum running it through a isolation transformer, beyond that Im not sure. Im sure this is a strange configuration but I would appreciate any feedback the resident experts would care to share.
The proposed plan is to install a 125 KVA onan generator on site to power the laser. I have suggested at a minimum running it through a isolation transformer, beyond that Im not sure. Im sure this is a strange configuration but I would appreciate any feedback the resident experts would care to share.