llo
Civil/Environmental
- Apr 3, 2003
- 3
A platform designed to be carried on piles in shallow water with each pile having a designed capacity a 40tons. Due to construction difficulty a piling hammer would not be suitable for the construction. However a vibro method would suffice, my problem is since the hammer efficiency is greater than the vibration method . Would the penetration depth be the same in both cases?. How do I establish a refusal/ acceptance criteria??