amazing azza
Industrial
- Apr 26, 2017
- 130
Hi guys, we are continuing our sugar plant build in sunny Indonesia.
We are about to begin work on laying the foundation. Foundation is going to be based on pre-cast, driven, concrete mini-piles. 2 rows of 10x3-pile, and 1 row of 10x2-pile (6m between pile packs lengthwise). Cone penetration testing locates a firm stratum (qc >250 barg) between 2.5 and 6 meters, based on 5 samples (4 corners + center).
1. How to deal with a large variance in depths (compared to overall pile length)? Piles of the size that we're using (250x250mm) come in 3m and 6m lengths, and have steel plates that can be welded together to form a joint.
- Order another round of cone penetration testing and make a detailed map?
- Use all piles at 6m long and just waste the excess?
- Use all piles in 3m long sections and splice as necessary?
2. Installation procedure. The pile cap will sit about 1m below grade, thus excavation will be necessary at some point. Would it be more prudent to:
- Excavate first, then drive?
- Drive first, then dig around the piles? And if so,
- Drive to below ground using an attachment?
- Drive above ground and cut to length once excavated for pile cap?
3. Should I validate the driving equipment before starting, ie. check the theoretical hard stratum depth vs actual driven depth? The contractor is planning on using a drop hammer driven by an electrical winch/roll with an operator that keeps pulling/letting go of a lever. It is quite rinky-dink compared to the kind of equipment you are probably used to. Nevertheless, that is "the standard" around here and it even seems to work...
We are about to begin work on laying the foundation. Foundation is going to be based on pre-cast, driven, concrete mini-piles. 2 rows of 10x3-pile, and 1 row of 10x2-pile (6m between pile packs lengthwise). Cone penetration testing locates a firm stratum (qc >250 barg) between 2.5 and 6 meters, based on 5 samples (4 corners + center).
1. How to deal with a large variance in depths (compared to overall pile length)? Piles of the size that we're using (250x250mm) come in 3m and 6m lengths, and have steel plates that can be welded together to form a joint.
- Order another round of cone penetration testing and make a detailed map?
- Use all piles at 6m long and just waste the excess?
- Use all piles in 3m long sections and splice as necessary?
2. Installation procedure. The pile cap will sit about 1m below grade, thus excavation will be necessary at some point. Would it be more prudent to:
- Excavate first, then drive?
- Drive first, then dig around the piles? And if so,
- Drive to below ground using an attachment?
- Drive above ground and cut to length once excavated for pile cap?
3. Should I validate the driving equipment before starting, ie. check the theoretical hard stratum depth vs actual driven depth? The contractor is planning on using a drop hammer driven by an electrical winch/roll with an operator that keeps pulling/letting go of a lever. It is quite rinky-dink compared to the kind of equipment you are probably used to. Nevertheless, that is "the standard" around here and it even seems to work...