Preeng1
Structural
- May 16, 2010
- 19
Hello:
I apologize in advance if my description is confusing:
I have a customer who wants us to erect a 50' x 325' x 18' arch shaped fabric building for them which has a concrete ballast block foundation system 4' high x 325' on one side (back wall) and each 50' end as the building has to be erected on wooden site mats at an oilfield site in northern B.C. and relocated within 4 to 5 months. No pilings or penetration of the site mats allowed.
The other side of the building is 13 doorways 25' wide for vehicle access and is to be framed using steel columns with I beam on top. The columns are 13' high and made from 6" x 6" x 3/8" wall hollow section and are 25' oc Each column has a plate welded with gussets on the bottom so that the column can be bolted to a "footing plate" that is 30" x 70" x 1" thick steel using 1" bolts.
Two 4,300 lb concrete ballast blocks will sit on the footing plates and be tied to it and the columns using steel ties with wedge anchors or epoxied anchors (that hasn't yet been specified)
The building frames which are welded truss frames 10' oc, are then mounted to the top of the concrete ballast blocks on the back wall but on the front wall are shorter to accommodate the door height of 13' so are to be mounted to a W10 x 49 I beam which sits on a plate welded with gussets to the top of the column and is atattched using 1" SAE Grade 5 bolts to connect the I beam to the column. The I beam is in sections and each section is connected using "fish plates"
The odd part is that they also have a 1,000 lb (max 2,000 lb) capacity chain hoist spanning the 50' width of the building on rails that run the entire 325' length on corbels which will be welded onto the face of the 6 x 6 columns to support the rails for the hoist. The back wall will also have the same columns with footing plates under the concrete ballast blocks in that wall to provide mounting for corbels on that side of the structure.
As each concrete block is 2' x 2' x 5' and weighs 4,300 lbs there is sufficient weight on the back wall which is continuous block except for a 24' opening at the mid point where an adjacent small fabric building ties into the other main building.
The back wall columns (supporting the crane only) will be braced easily as there are no restrictions except bolted construction and the small building opening that will be spanned by a small I beam to carry the load from the main building frames over the opening.
The crane rails will also be sectional as again the whole thing has to be moved in the not too distant future.
Pheew, finally, my question is what will the building or crane do if there is significant heaving in winter - spring thaw cycles or is that not a concern due to the weight - design of the building and foundation system ?
The vehicles which will be inside when the structure - crane is in use add about 10 tons per doorway to the site mat, block, I beam, columns, crane rails, crane and other weight.
The building is heated to just above freezing and when erected will be in continuous use until the proeject is finished when it will be dismantled, relocated and re-erected at another site for the same purpose.
Thanks in advance for any comments, input or thoughts
Bob
MBC International
Pre-engineered Building Systems
I apologize in advance if my description is confusing:
I have a customer who wants us to erect a 50' x 325' x 18' arch shaped fabric building for them which has a concrete ballast block foundation system 4' high x 325' on one side (back wall) and each 50' end as the building has to be erected on wooden site mats at an oilfield site in northern B.C. and relocated within 4 to 5 months. No pilings or penetration of the site mats allowed.
The other side of the building is 13 doorways 25' wide for vehicle access and is to be framed using steel columns with I beam on top. The columns are 13' high and made from 6" x 6" x 3/8" wall hollow section and are 25' oc Each column has a plate welded with gussets on the bottom so that the column can be bolted to a "footing plate" that is 30" x 70" x 1" thick steel using 1" bolts.
Two 4,300 lb concrete ballast blocks will sit on the footing plates and be tied to it and the columns using steel ties with wedge anchors or epoxied anchors (that hasn't yet been specified)
The building frames which are welded truss frames 10' oc, are then mounted to the top of the concrete ballast blocks on the back wall but on the front wall are shorter to accommodate the door height of 13' so are to be mounted to a W10 x 49 I beam which sits on a plate welded with gussets to the top of the column and is atattched using 1" SAE Grade 5 bolts to connect the I beam to the column. The I beam is in sections and each section is connected using "fish plates"
The odd part is that they also have a 1,000 lb (max 2,000 lb) capacity chain hoist spanning the 50' width of the building on rails that run the entire 325' length on corbels which will be welded onto the face of the 6 x 6 columns to support the rails for the hoist. The back wall will also have the same columns with footing plates under the concrete ballast blocks in that wall to provide mounting for corbels on that side of the structure.
As each concrete block is 2' x 2' x 5' and weighs 4,300 lbs there is sufficient weight on the back wall which is continuous block except for a 24' opening at the mid point where an adjacent small fabric building ties into the other main building.
The back wall columns (supporting the crane only) will be braced easily as there are no restrictions except bolted construction and the small building opening that will be spanned by a small I beam to carry the load from the main building frames over the opening.
The crane rails will also be sectional as again the whole thing has to be moved in the not too distant future.
Pheew, finally, my question is what will the building or crane do if there is significant heaving in winter - spring thaw cycles or is that not a concern due to the weight - design of the building and foundation system ?
The vehicles which will be inside when the structure - crane is in use add about 10 tons per doorway to the site mat, block, I beam, columns, crane rails, crane and other weight.
The building is heated to just above freezing and when erected will be in continuous use until the proeject is finished when it will be dismantled, relocated and re-erected at another site for the same purpose.
Thanks in advance for any comments, input or thoughts
Bob
MBC International
Pre-engineered Building Systems