I have a project where we are cutting some new small openings in existing tilt panels (Seismic design category D). The plan reviewer has requested "reinforcement, or metals equivalent to 2-#5 all around concrete wall opening".
Does anyone know why this might be needed? I don't need it for strength. Unfortunately, the reviewer is out of the office- and we are trying to resubmit as fast as possible
Thanks
Does anyone know why this might be needed? I don't need it for strength. Unfortunately, the reviewer is out of the office- and we are trying to resubmit as fast as possible