Thank you for your reactions.
The piles are atlas piles, full displacement piles.
The project is in the Netherlands.
There was no casing used, not even a temporary casing.
The overconsumption shows there should be bulging at lower depths, as we assume.
the diameter of piles is 560mm/460mm. and the necking diameter was found to be 240mm, some piles are crushed.
Manufacture.
A steel pipe onto which a replaceable auger head is fastened at the bottom is pressed into the ground in a screwing motion. Due to the auger head, the soil is laterally displaced or compacted. The auger head is sealed water-tight with a lost closing nut tip.
The auger head and the pipe are screwed vibration-free into the ground using a rotary drive with simultaneous pressure. The hydraulic drive pressure is measured when it is screwed in and compared with the foundation soil information, such as the drilling profiles, sounding diagrams, etc. After achieving the required drive pressure, the reinforcing cage is inserted. The pipe and the reservoir are filled with concrete. The pipe and the auger head are withdrawn by screwing them backward. During this process, the base tip is released and the auger head forms the thread-like pile. The concrete column in the pipe and reservoir with its large static overpressure immediately fills the released cavity with concrete. Therefore, a spiral concrete bulge approximately 5 cm in thickness is formed in the ground around the pile shaft.
Soil profile:
first layer: sand (2m thickness)
second layer: clay (3.2m thickness) - necking occurred in this layer.
the lowest Cu value(undrained shear strength) found in this second clay layer is 25kpa.
According to the site contractor, the concrete head was maintained properly.