JoeBaseplate
Structural
- May 31, 2011
- 204
I have seen number ranging from 1500-2500 psi depending on the engineer and the firm creating the drawings. I am used to 1800 psi but was recently suggested by a more seasoned engineer that this may be too conservative and I should use 2000 psi minimum as typically thats a minimum number the cmu supplier can provide.
So my obvious question is, whats the economical and readily available f'm.