On 2015IRC 404.1.6 requires for "the foundation to extend above the finished grade a minimum of 4 inches where masonry veneer is used and a minimum to 6 inches elsewhere." But I do not find the equivalent for this requirement on the IBC for non-residential structures. I reviewed 2015 IBC chapter 18 but cannot find this type requirements. Please help!
 
Another prime example of why adhering to minimum code is poor engineering. With climate change , increasing weather events and horrendous flooding everywhere , anything less than 16 inches seems criminally irresponsible to me
 
The finished grade is usually set 6" to 12" below the 1st floor, and sloped away from the structures.
 
This thread may be of interest:
thread194-417230
 