I am mainly inquiring about how vertical control joints are installed at wall openings when a masonry bond beam spans/extends across the opening. How is a vertical CJ installed?
I have a small addition 50' x 30' that utilizes reinf. cmu behind a stone veneer and inside finish is mtl. stud/drywall, so the reinf. cmu is never visible. The 50' span has many door, window openings.
Thanks
I have a small addition 50' x 30' that utilizes reinf. cmu behind a stone veneer and inside finish is mtl. stud/drywall, so the reinf. cmu is never visible. The 50' span has many door, window openings.