I build alot of injection molds in Asia, and one problem I run into is that the tool maker rushes to send me parts off of the tool (that I approved the tool design to) before some things are complete. I am sure this is for payment.
For example, the first samples from my last project the tool was ran without water lines being hooked up and a very long cycle. I have requested a video of these samples which has helped to some degree.
What I would like to know is, is there anyone that has made a tool approval spec sheet?
This would have things like cycle time and ejection methods, maybe steel temp after so long of a run, things of that nature.
I do travel to Asia freequently but I feel for the times I cant I need to make these tool shops accountable.
For example, the first samples from my last project the tool was ran without water lines being hooked up and a very long cycle. I have requested a video of these samples which has helped to some degree.
What I would like to know is, is there anyone that has made a tool approval spec sheet?
This would have things like cycle time and ejection methods, maybe steel temp after so long of a run, things of that nature.
I do travel to Asia freequently but I feel for the times I cant I need to make these tool shops accountable.