- Apr 15, 2010
- 187
I seem to come across an issue a lot that I don't know what to do with.
Often when checking bearing pressure under service loads I have no uplift across the footing. As soon as I factor my loads though I do get uplift.
In other words, the load factors change the structural support. The concrete design loads are now based on a an altered support condition influenced by load factors. This doesn't seem like a realistic approach to me. Any comments or thoughts?
Often when checking bearing pressure under service loads I have no uplift across the footing. As soon as I factor my loads though I do get uplift.
In other words, the load factors change the structural support. The concrete design loads are now based on a an altered support condition influenced by load factors. This doesn't seem like a realistic approach to me. Any comments or thoughts?