Dear all

During Tender process Contractor provided discount on overall amount of works in BoQ.
In BOq summary contingency is provided 9%.

My question is:
For new unit rates paid according to detailed breakdown submitted (market prices), should we apply discount given to overall sum in Contract BoQ?