I need to extend a 3" schedule 40 pipe sleeve (wall thickness 0.216 inches). This will involve chipping away the concrete around the pipe, and welding on a 4 inch extention. We are doing this so we can pour a concrete curb around the extended sleeve. How should the new sleeve be welded on? Could I show a symbol for a square weld, and label it PJP with no size given? There is no load on this weld, we just want the sleeve to be sealed. Thanks!
I need to extend a 3" schedule 40 pipe sleeve (wall thickness 0.216 inches). This will involve chipping away the concrete around the pipe, and welding on a 4 inch extention. We are doing this so we can pour a concrete curb around the extended sleeve. How should the new sleeve be welded on? Could I show a symbol for a square weld, and label it PJP with no size given? There is no load on this weld, we just want the sleeve to be sealed. Thanks!