StarkInc14
Structural
- Oct 15, 2019
- 6
HELLO GUYS.
IM CURRENTLY MODELING A CONCRETE BUILDING AND I HAVE A QUESTION WITH REGARDS TO WHAT WOULD BE THE CORRECT MODELING TECHNIQUE. I FIRST WOULD LIKE TO GIVE SOME BACKGROUND INFORMATION ON MY CASE.
MY CONCRETE BUILDING CONSISTS OF AN 18 STORY BUILDING. DUE TO SOME ARCHITECTURAL CONSTRAINT I CANNOT KEEP A SHEAR WALL THAT STARTS FROM THE CELLAR CONTINUOUS TO THE ROOF. THE SHEAR WALL ENDS AT THE 10TH FLOOR AND THE ABOVE FLOORS ARE SUPPORTED BY 2 COLUMNS THAT PROTRUDE FROM THE SHEAR WALL BELOW AND CONTINUE TO THE ROOF. THE COLUMNS THAT CONTINUE TO THE ROOF ARE THE SAME THICKNESS AS THAT OF THE SHEAR WALL BELOW (18 INCHES THICK).
MY QUESTIONS ARE THE FOLLOWING: WHAT IS THE CORRECT WAY I MODEL THIS SITUATION. SHOULD I CONTINUE TO MODEL THE COLUMNS (THAT TECHNICALLY END AT THE 10TH FLOOR)ALL THE WAY TO THE CELLAR AS A COLUMN MEMBER, AND DRAW THE SHEAR WALL IN BETWEEN THE COLUMNS FROM CELLAR TO THE 10TH FLOOR (OPTION 1)? OR, SHOULD I KEEP THE "COLUMN MEMBERS" FROM ROOF TO 10TH FLOOR, AND THEN BELOW THE 10TH FLOOR JUST DRAW THE SHEAR WALL ONLY BUT MAKING SURE THAT THE WALL IS MANUALLY MESHED WHERE THE COLUMN NODE IS LOCATED ABOVE (OPTION 2)? SINCE BOTH THE COLUMN AND SHEAR WALL ARE OF SAME THICKNESS, THE LOAD FROM COLUMN ESSENTIALLY DISTRIBUTE TO THE WALL I JUST DONT KNOW IF MODELING ONE WAY IS MORE CORRECT THAN THE OTHER. I HAVE ATTACHED AN IMAGE TO HELP VISUALIZE MY SITUATION.
YOUR HELP IS ALWAYS APPRECIATED.
IM CURRENTLY MODELING A CONCRETE BUILDING AND I HAVE A QUESTION WITH REGARDS TO WHAT WOULD BE THE CORRECT MODELING TECHNIQUE. I FIRST WOULD LIKE TO GIVE SOME BACKGROUND INFORMATION ON MY CASE.
MY CONCRETE BUILDING CONSISTS OF AN 18 STORY BUILDING. DUE TO SOME ARCHITECTURAL CONSTRAINT I CANNOT KEEP A SHEAR WALL THAT STARTS FROM THE CELLAR CONTINUOUS TO THE ROOF. THE SHEAR WALL ENDS AT THE 10TH FLOOR AND THE ABOVE FLOORS ARE SUPPORTED BY 2 COLUMNS THAT PROTRUDE FROM THE SHEAR WALL BELOW AND CONTINUE TO THE ROOF. THE COLUMNS THAT CONTINUE TO THE ROOF ARE THE SAME THICKNESS AS THAT OF THE SHEAR WALL BELOW (18 INCHES THICK).
MY QUESTIONS ARE THE FOLLOWING: WHAT IS THE CORRECT WAY I MODEL THIS SITUATION. SHOULD I CONTINUE TO MODEL THE COLUMNS (THAT TECHNICALLY END AT THE 10TH FLOOR)ALL THE WAY TO THE CELLAR AS A COLUMN MEMBER, AND DRAW THE SHEAR WALL IN BETWEEN THE COLUMNS FROM CELLAR TO THE 10TH FLOOR (OPTION 1)? OR, SHOULD I KEEP THE "COLUMN MEMBERS" FROM ROOF TO 10TH FLOOR, AND THEN BELOW THE 10TH FLOOR JUST DRAW THE SHEAR WALL ONLY BUT MAKING SURE THAT THE WALL IS MANUALLY MESHED WHERE THE COLUMN NODE IS LOCATED ABOVE (OPTION 2)? SINCE BOTH THE COLUMN AND SHEAR WALL ARE OF SAME THICKNESS, THE LOAD FROM COLUMN ESSENTIALLY DISTRIBUTE TO THE WALL I JUST DONT KNOW IF MODELING ONE WAY IS MORE CORRECT THAN THE OTHER. I HAVE ATTACHED AN IMAGE TO HELP VISUALIZE MY SITUATION.
YOUR HELP IS ALWAYS APPRECIATED.