Hi all. I was recently promoted to design lead at a small-midsize company. Prior to my promotion there had been no direct management of this department. Engineering managers made some decisions when it was needed, but never developed any processes or standards for the design department. Now, I'm trying to bring some order to the chaos. We have no PDM/PLM, which makes the task of processing 100+ drawings very painful.
Our undefined, unofficial "process" for a drawing from creation to sign-off is as follows
[ul]
[li]Engineering provides Design a list of drawings/revisions to be created/updated. This list can be provided before or during the drawing creation/update. This list can be modified at any time during the drawing creation/update process.[/li]
[li]Design creates/updates drawings to the best of their abilities and submits printed drawings to the checker.[/li]
[li]Checker checks drawings and returns marked up print to designer[/li]
[li]Designer makes corrections to drawing per mark up and returns corrected print to checker. Repeat until checker is happy.[/li]
[li]Checker gives drawing to engineer to review[/li]
[li]Engineer reviews and marks up drawing and gives to designer[/li]
[li]Designer makes corrections and gives to checker.[/li]
[li]Checker reviews/mark up drawing. If drawing is good, it goes to engineer. Otherwise, it is returned to the designer for corrections.[/li]
[li]When engineer is happy, drawing is submitted to engineering manager. Drawing is corrected until engineering manager is happy.[/li]
[li]Drawing is stamped/released[/li]
[/ul]
To me this seems insanely inefficient. The drawings can just...swirl until all parties are happy and our due dates just sail on by.
Could someone please tell me how this is done in the rest of the world? Or, could you point me to an online resource about this?
Thanks,
D
Our undefined, unofficial "process" for a drawing from creation to sign-off is as follows
[ul]
[li]Engineering provides Design a list of drawings/revisions to be created/updated. This list can be provided before or during the drawing creation/update. This list can be modified at any time during the drawing creation/update process.[/li]
[li]Design creates/updates drawings to the best of their abilities and submits printed drawings to the checker.[/li]
[li]Checker checks drawings and returns marked up print to designer[/li]
[li]Designer makes corrections to drawing per mark up and returns corrected print to checker. Repeat until checker is happy.[/li]
[li]Checker gives drawing to engineer to review[/li]
[li]Engineer reviews and marks up drawing and gives to designer[/li]
[li]Designer makes corrections and gives to checker.[/li]
[li]Checker reviews/mark up drawing. If drawing is good, it goes to engineer. Otherwise, it is returned to the designer for corrections.[/li]
[li]When engineer is happy, drawing is submitted to engineering manager. Drawing is corrected until engineering manager is happy.[/li]
[li]Drawing is stamped/released[/li]
[/ul]
To me this seems insanely inefficient. The drawings can just...swirl until all parties are happy and our due dates just sail on by.
Could someone please tell me how this is done in the rest of the world? Or, could you point me to an online resource about this?