Mar 9, 2021 #1 UtlSer Structural Joined Jan 21, 2021 Messages 3 Location AU Wondering if you connect the lower basement slab to piers & infill shotcrete wall using dowels and why?
Wondering if you connect the lower basement slab to piers & infill shotcrete wall using dowels and why?
Mar 9, 2021 #2 Retrograde Structural Joined Aug 26, 2015 Messages 613 Location AU One reason to do it is if you are relying on the slab to offer lateral restraint to the retaining wall. Upvote 0 Downvote
One reason to do it is if you are relying on the slab to offer lateral restraint to the retaining wall.
Mar 9, 2021 Thread starter #3 UtlSer Structural Joined Jan 21, 2021 Messages 3 Location AU But piers are used already and thus provide restraints to the wall. Even if you want the wall to span vertically from slab-on-grade to the upper one, the construction sequence will require you to span horizontally during excavation. Upvote 0 Downvote
But piers are used already and thus provide restraints to the wall. Even if you want the wall to span vertically from slab-on-grade to the upper one, the construction sequence will require you to span horizontally during excavation.
Mar 10, 2021 #4 Retrograde Structural Joined Aug 26, 2015 Messages 613 Location AU Yes but often temporary anchors or bracing is installed to provide support to the wall until the slabs are in place. Upvote 0 Downvote
Yes but often temporary anchors or bracing is installed to provide support to the wall until the slabs are in place.