JackTrades
Structural
- Jan 27, 2005
- 53
I've been presented with a problem concerning an existing tied-back diaphragm (or slurry) wall in which an additional excavation to 15 feet below the bottom of the wall is required. One solution put forth is to place an additional diaphragm wall at the face of the existing, extending down to a sufficient depth below the proposed new excavation elevation and adding soil anchors through the new and existing wall as necessary.
I am concerned about two issues:
1. That the bennonite slurry will not provide any passive resistance pressure prior to the placing and hydration of the reinforced concrete in the new wall possibly allowing the existing wall to fail at the toe, shearing off the rock ledge upon which it sits, due to its weight and the existing vertical component force of the anchors.
2. That the soil angle failure plane, moving down to the tip of the new wall toe from the existing wll toe, will intersect the existing anchor grout zones.
(The attached sketches might provide a better explanation of the situation than I can describe.)
My questions are:
1. If I limit the width of the new slurry wall segments, say to 6 feet, would that allow for the redistribution of passive soil resistance from the trenched area to the adjacent wall areas to each side?
2. Is there some way to adjust or modify the theoretical failure angle that will originate from the toe of the new wall so as to see if it might miss the grouted anchor zones?
3. Is there a better way to tackle this problem?
(I'm a structural engineer, not a geotech, so please speak slowly and in Sesame Street terms if you reply.)
Any advice will be greatly appreciated.
Jack
I am concerned about two issues:
1. That the bennonite slurry will not provide any passive resistance pressure prior to the placing and hydration of the reinforced concrete in the new wall possibly allowing the existing wall to fail at the toe, shearing off the rock ledge upon which it sits, due to its weight and the existing vertical component force of the anchors.
2. That the soil angle failure plane, moving down to the tip of the new wall toe from the existing wll toe, will intersect the existing anchor grout zones.
(The attached sketches might provide a better explanation of the situation than I can describe.)
My questions are:
1. If I limit the width of the new slurry wall segments, say to 6 feet, would that allow for the redistribution of passive soil resistance from the trenched area to the adjacent wall areas to each side?
2. Is there some way to adjust or modify the theoretical failure angle that will originate from the toe of the new wall so as to see if it might miss the grouted anchor zones?
3. Is there a better way to tackle this problem?
(I'm a structural engineer, not a geotech, so please speak slowly and in Sesame Street terms if you reply.)
Any advice will be greatly appreciated.
Jack