civie316 -
That sounds like my challenge as my first job as field inspector for the highway department (engineering student on a summer job). We were driving freshly creosoted wood piles for freeway bridges and abutments on a 85-90F day. Since I was new, they gave me the OPPORTUNITY(?) to determine when we got deep enough.
We used one or two saw horses with grooves as a guide for a long steel rod with a spike to determine the driving distance every ten blows ( the criteria was 1" per 10 blows). The levelness of the rod/spike was not too critical since the closest saw horse was close to the wood piling.
When I got home that day, I had burns on my arms, back and front(through my shirt) from the hot, fresh creosote and oil from the driver. - It was a great experience that I never will forget, and it not necessary to get so close since you are looking at a relative driving length if you are close to the piles. - I was the eager "greenie" that everyone thought needed some experience.
Long steel piles are a different story. In another episode as a project engineer we were driving long steel piles (some spliced) through a mine waste dump where the anticipated solid rock bearing was about 70' to 100'. We had a pile that was spliced and driving continued and we had to decide if we wanted to go deeper. We got my answer when I leaned against another previously driven pile 50' feet away that resounded when the driver hit. - The pile had hit a large (2' - 6') rock from the stripping and got deflected and bent in a large curve horizontally about 50'. Keep in mind that steel pile can be gradually deflected and may not got directly in line with the surface exposure above grade.
don't split hairs for a 1" increment.
Dick
Engineer and international traveler interested in construction techniques, problems and proper design.