palves
Structural
- Jun 6, 2008
- 61
I have a project where the architect is applying a waterproofing membrane over the top of some concrete work we are doing. The architect does not want the waterproofing to be damaged when the concrete cracks and would like to know how long he should wait after placement before applying the waterproofing. This is a nonstructural topping slab so I am basically trying to determine how long it takes for the majority of shrinkage cracks to occur. Any ideas out there?
Also, I know there is a graph showing the percentage of shrinkage cracking vs time but cannot for the life of me track it down. Can anybody point me in the right direction to finding that?
Also, I know there is a graph showing the percentage of shrinkage cracking vs time but cannot for the life of me track it down. Can anybody point me in the right direction to finding that?