KCAP
Structural
- Mar 25, 2022
- 2
So sorry to have to bring this to the discussion but unexpected turn has left me no choice. I have common trusses made of 2 x 4s spanning 23.5 feet. I was knocking down a wall (perpendicular and midpoint to trusses) and decided I wanted to place an lvl up in the attic with some simpson ties for piece of mind (the trusses technically don't need that wall but it's an older home where they were made on site so I wanted to cover my bases). Unfortunately, the carpenters cut through the bottom chord of 2 of the trusses (at midpoint) before I could catch it(unbelieveable). Will adding a 12 foot 2 x 4 on either side of the damaged trusses provide adequate support to complete my job? If so, I believe I also need alternating kicker braces along the 16 ft lvl. Would those go from the top of the lvl back 4-5 feet and then still braced on the bottom chord of the truss? Should I block the damaged trusses some on either side as well? Seems basic, but the setback has got me second guessing now. Thanks so much in advance to everyone.