Can anybody clarify my followinG doubts about column end conditions:
1. A steel column with base plate and 2 or 4 anchors and 300 below finish floor is considered as "fixed" support or "pinned" support in analysis.
2. In cantilever beam construction, the column end with a W beam resting on top of column, is considere "pinned" or "fixed".
Thanks
1. A steel column with base plate and 2 or 4 anchors and 300 below finish floor is considered as "fixed" support or "pinned" support in analysis.
2. In cantilever beam construction, the column end with a W beam resting on top of column, is considere "pinned" or "fixed".