ship4885
Structural
- May 19, 2009
- 17
The building I am workign on has a significant portion of the building cantilevered out. We have created 3 large trusses that carry this cantilever slab, that look like giant P's. Since the cantilevered portion of the floor is longer than the backspan, we have significant uplift on the first column of each of the trusses. There is ALWAYS a tension on these columns. Are there any special code provisions to consider with a column that is always in tension?