rahuldby
Structural
- Mar 21, 2004
- 22
Do we need to provide a closure strip for a typical one-way PT slab to eliminate restraint cracking? The length of the building is about 350 ft. The post tensioning manual suggests to consider two closure strips for slab length between 325 and 400 ft. Does anyone have experience of not having any closure strips under similar situations? Any thoughts and suggestings would be appreciated. Thanks.