Can you do process piping B31.3 welding work with B31.1 quality control manual

Status
Not open for further replies.

stanweld99

Nuclear
Joined
May 2, 2013
Messages
27
Location
CA
I know there is no stamp requriement for the process piping B31.3. We have PP and S stamps and quality control manual for B31.1 and Asme Section I. But the QC manual does not mention anything about B31.3. My question is: Can we do B31.3 process piping welding work with the QC manual we have.
Thanks for your help.
 
Your Code Quality Manual is not applicable to B31.3 work; however, the basics are similar. Note that the Inspector for B31.3 work is the Owner/Operator's Inspector - not an AI. B31.3 is Owner driven while the Boiler Code is not.
 
Thanks for the reply. It is very helpful.
 