Continue to Site

Eng-Tips is the largest engineering community on the Internet

Intelligent Work Forums for Engineering Professionals

  • Congratulations cowski on being selected by the Eng-Tips community for having the most helpful posts in the forums last week. Way to Go!

Can a WPS/ PQR written to D1.1 be used for API 6A

Status
Not open for further replies.

JACOB07

Structural
May 16, 2012
1
i have a customer that is an api 6a services shop

They had a wps and pqr made up but was written to aws d1.1 but the requirements need to be API 6A and NACE.If all requirements are meet can this procedure be used? The only problem i see with it is there was no charpys performed and from what i was reading charpys testing needs to be done in the weld and HAZ and satisfy the Base metal requirements which is 4130.Any help would be greatly appreciated.
 
Replies continue below

Recommended for you

Without seeing the WPS, can't really tell you anything. But from seeing other Procedures, only written to AWS, the WPS wasn't even close to API requirements.

Petrotrim Services
 
Based on the old PQR test conditions and test results a new WPS can be written(as per sec IX which meets requirements of API 6A).If the WPS is written satisfying the conditions of the sec IX then i hope it wouldnt be a problem.
 
mettamadhan,
You cannot take an AWS D1.1 PQR and write an ASME IX WPS from this.
When the coupon was originally tested it could have been tested to dual codes (if there was sufficient material for all required tests) but you cannot do as you have suggested.
Regards,
Kiwi
 
Jacob07,
No, ASME IX qualification is required,
Regards,
Kiwi

TITLE:
PROCEDURE QUALIFICATION & PRODUCTION WELDING
REQUIREMENTS FOR FUSION WELDING
PRESSURE CONTAINING AND LOAD BEARING WELDMENTS IN
ACCORDANCE WITH API 6A & API 16A SUPPLEMENT
t.
1. SCOPE:
1.1 This specification defines a) the minimum requirements for joining and repairing
pressure containing and load bearing weldments by fusion welding, b) the
minimum requirements for qualifying fusion-welding procedures, and c) the technical
reasons for each set of requirements. (Parenthetical references are listed in Appendix
C.)
1.2 The requirements of this specification apply to all facilities that manufacture, overhaul,
or repair products for Hydril, including Hydril authorized vendors and Hydril authorized
repair facilities.
2. GENERAL REQUIREMENTS
2.1 Welding of all pressure containing and non-pressure containing weldments
exposed to well bore fluids shall be performed with procedures qualified in accordance
with this specification.
2.2 Welding of all pressure containing and load bearing weldments not exposed to well
bore fluids shall also be performed with procedures qualified in accordance with this
specification except that the material and hardness requirements need not conform to
NACE MR0175.
2.3 All welders and welding operators shall be qualified in accordance with the
requirements of the ASME Boiler & Pressure Vessel Code Section IX.

Full text here
 
Status
Not open for further replies.

Part and Inventory Search

Sponsor