GemmellG
Materials
- Jun 28, 2012
- 89
Can anyone point me in the right direction were the decides where the code break between BEP (B31.1. & NBEP (B31.3) Assembling ASME Sec 1 boiler. P&ID & LDT shows the piping upstream of Boiler External piping (B31.1)after the stop check valve is ASME B31.3. Authorized Inspector (AI) is adamant this piping should be NBEP (B31.1).