Has anyone had success modeling back-to-back storms?

I tried entering in "2" in the back-to-back storms calculation setting. Then, I tried the storm duration setting at both 24hr and 48hr. The resulting hydrograph still only runs one storm. Any suggestions?

Thanks,
Chad
 
Forget it. I figured it out.
 
When you use back-to-back storms you generally need to increase the calculation time span, otherwise the second storm may fall outside the visible window. The storm is there - you just can't see.
 