dursosono
Materials
- Aug 6, 2008
- 59
Is there any statement in B31.4 that cite the two additional joint shall be inspected when the result of a joint girth weld reveal "rejected"?
This is a flowline with hydrocarbon services. RT was performed by 10% randomly.
This is a flowline with hydrocarbon services. RT was performed by 10% randomly.