If indeed the problem was external to Grenfell Tower, then the cause of the electrical problems should have been recorded. Peter Maddison – Director of Assets and Regeneration, the Head Honcho for KCTMO on the Grenfell Refurbishment project, told the RBKC Council that subsequent to the power failure, monitoring equipment (Data Logger) had been set up. If the data-logger was set up externally, wouldn't this have been done by UKPN, the power distributor or does/can one hire a contractor to perform supply side monitoring? What good would private data logging serve if the issue was caused by UKPN? If the Neutral Fault was external, how did KCTMO's contractor find it, via an in ground vault outside the tower, excavation? Supposedly the root of the problem was finally discovered over a 12 hour period, when all the residents had their power shut off by the contractor.
Leadbitter working on the KALC project adjacent to Grenfell Tower, denied that their work had anything to do with the power problems at Grenfell Tower. Here is a pre-construction site plan that, as near as I can tell, shows the power supply to Grenfell at the South side of the tower, running East, then Northeast across the park, up to Verity Close & on to Silchester Road;
bisecting the KALC Project.
Link
Surely at some point in the work done on the KALC project the power to Grenfell had to have been a complication. Maybe the original site work was fine and the temporary work around was not. That is, if the site plan & my interpretation is accurate.
When Peter Maddison – KCTMO Director of Assets and Regeneration told the RBKC Council's Housing & Property Scrutiny Committee that some of the residents had confused smoke with steam & the bulk of the Committee bought into this nonsense, it becomes hard to believe the Council was concerned with anything more than being able to distance themselves from the problem and thus the entire exchange between the Council Committee & KCTMO becomes suspect. It seems only the Council Woman representing the Estate took offense with the explanation. Anytime I've been offered mealy-mouthed explanations that stoop to implying utter stupidity by some other party, my confidence in the person voicing the the explanation takes a nose-dive. How does one confuse the acrid smell of an electrical fault with steam?
So the setting is as follows:
A contractor is working adjacent to Grenfell Tower, whose work may or may not have been the cause of power problems at Grenfell Tower.
A power problem that by resident accounts went on for 3 weeks leading to a catastrophic power event.
45 Flats, all on the upper floors of Grenfell Tower experiencing some loss of property because of the catastrophic power event.
Full renewal of Grenfell's rising electricity main.
And subsequent Data Logging.
No suggestions by the Council or KCTMO that Max Fordham, the Mechanical & Electrical Consultant for both the KALC & Grenfell Projects, make any kind of a Survey of the Grenfell Tower electrical services in advance of the refurbishment project.
I am ignorant on electrical but how does an external fault, fry appliances on just the upper floors, over 30% of the flats. Presumably, fry the main electrical riser yet the lower & intermediate floors are unaffected, even though they all experienced power issues? Separate mains?
It is too bad that none of the resident groups never thought to make a freedom of information request for the Data Logging. Most information regarding Council property operations are run through the Tenant Management Organization and KCTMO is a private enterprise, so it is a freedom of information black-hole but KCTMO doesn't own the property, the Council does so, a freedom of information request on the UKPN data-logging to Grenfell Tower may have been a Power Distributor/Owner record beyond the power of KCTMO to keep private.