INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Contact US

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Problem calculating the quantity of argon gas required for a GTAW (TIG) process

Problem calculating the quantity of argon gas required for a GTAW (TIG) process

Problem calculating the quantity of argon gas required for a GTAW (TIG) process

(OP)
Please could some assist me with the solution for calculating the quantity of argon gas required to weld (Root and Hot) pass in a 22'' 28.58 mm thick CS pipe with GTAW process. Thank you.

RE: Problem calculating the quantity of argon gas required for a GTAW (TIG) process

No way to estimate that with any precision; there are just too many variables.
The expression 'YMMV' is very apt here.

"Everyone is entitled to their own opinions, but they are not entitled to their own facts."

RE: Problem calculating the quantity of argon gas required for a GTAW (TIG) process

(OP)
Ok. Thanks.

RE: Problem calculating the quantity of argon gas required for a GTAW (TIG) process

Depending on the material to be welded and what it's for you may be using backing gas as well for the root pass.

your total would be the volume of gas a minute including backing gas in lt/min multiples by time to complete the root pass plus torch flow to complete the hot pass and then the capping passes.

RE: Problem calculating the quantity of argon gas required for a GTAW (TIG) process

Assuming welding is in a shop, 15 CFH argon flow would be normal. Calculate the amount of time to make the pipe weld and then compute. You're not going to do much better than averaging 3" per minute travel speed with manual GTAW with pipe in the fixed position. Higher travel speeds would be expected if pipe were rotated. All above advice is off when welding is done in the field - oh so many variables.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

Low-Volume Rapid Injection Molding With 3D Printed Molds
Learn methods and guidelines for using stereolithography (SLA) 3D printed molds in the injection molding process to lower costs and lead time. Discover how this hybrid manufacturing process enables on-demand mold fabrication to quickly produce small batches of thermoplastic parts. Download Now
Design for Additive Manufacturing (DfAM)
Examine how the principles of DfAM upend many of the long-standing rules around manufacturability - allowing engineers and designers to place a part’s function at the center of their design considerations. Download Now
Taking Control of Engineering Documents
This ebook covers tips for creating and managing workflows, security best practices and protection of intellectual property, Cloud vs. on-premise software solutions, CAD file management, compliance, and more. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close