INTELLIGENT WORK FORUMS
FOR ENGINEERING PROFESSIONALS

Log In

Come Join Us!

Are you an
Engineering professional?
Join Eng-Tips Forums!
  • Talk With Other Members
  • Be Notified Of Responses
    To Your Posts
  • Keyword Search
  • One-Click Access To Your
    Favorite Forums
  • Automated Signatures
    On Your Posts
  • Best Of All, It's Free!
  • Students Click Here

*Eng-Tips's functionality depends on members receiving e-mail. By joining you are opting in to receive e-mail.

Posting Guidelines

Promoting, selling, recruiting, coursework and thesis posting is forbidden.

Students Click Here

Jobs

Can I use a WPS previous

Can I use a WPS previous

Can I use a WPS previous

(OP)
Friends:

Can I use a WPS under asme B31.3 used with the same client years ago.

My client indicates that it must be re-qualified.

Thank for your help.


JATE




RE: Can I use a WPS previous

Not exactly what you are looking for...but shows requalification is not required.

Standard Designation: BPV Section IX
Edition/Addenda:
Para./Fig./Table No:
Subject Description: QW-100.3 and QW-200.2, Procedure Qualification Record Time Limits
Date Issued: 06/10/2004
Record Number: BC04-601
Interpretation Number : IX-04-10
Question(s) and Reply(ies):

Question: Is there a time limit on the validity of a PQR?

Reply: PQRs always remain valid but may only be used to support WPSs, provided they meet the requirements of the 1962 or later Edition of ASME Boiler and Pressure Vessel Code Section IX. See QW-100.3.

RE: Can I use a WPS previous

If your customer has time limits to requalify a WPS (some do), that's one thing. But if they are saying ASME has a time limit, that's not correct (other than the 1962 limit)

RE: Can I use a WPS previous

B31.3 section 328.2.2. seems to apply here. No mention of maximum time, but

The key phrase is "subject to the approval of the owner".

It seems you don't have that approval.

So can you use it - Yes
Does the owner/client accept this - Up to him/her. See what the welding specification / construction specification says.

I've often seen a 6 month time window imposed on WPS qualification testing.

I think those clause got written in by the testing companies....

Remember - More details = better answers
Also: If you get a response it's polite to respond to it.

RE: Can I use a WPS previous

328.2.2 deals with a WPS qualified by others...This is there own procedure.

RE: Can I use a WPS previous

It only says they "used" a WPS, not that they created it....

Either way I think the point stands - the client wants one thing but hasn't said where this requirement was specified.

Remember - More details = better answers
Also: If you get a response it's polite to respond to it.

Red Flag This Post

Please let us know here why this post is inappropriate. Reasons such as off-topic, duplicates, flames, illegal, vulgar, or students posting their homework.

Red Flag Submitted

Thank you for helping keep Eng-Tips Forums free from inappropriate posts.
The Eng-Tips staff will check this out and take appropriate action.

Reply To This Thread

Posting in the Eng-Tips forums is a member-only feature.

Click Here to join Eng-Tips and talk with other members! Already a Member? Login


Resources

eBook - Manufacturing the Cars of Tomorrow
In this ebook, we'll explore how additive manufacturing is going to transform the way cars are made. This includes commentary from thought leaders such as Ford's CTO, Ken Washington, Customer case studies of ways 3D printing is being used today, and a variety of part examples where 3D printing is already impacting how automobiles are made. Download Now
White Paper - Smart Manufacturing for Semiconductor
New technologies and approaches present great opportunities for semiconductor manufacturers to achieve high levels of innovation, yield and improvement. This white paper explores some of these cutting-edge technologies and how they can be applied effectively in the semiconductor industry. Read about how Smart Manufacturing is transforming the semiconductor industry. Download Now
White Paper - Analysis and Simulation in Aircraft Structure Certification
Organizations using simulation and analysis tools effectively see the benefits in their ability to achieve certification faster and with drastically less total cost than those who do not maximize these tools. Read this White Paper to learn about how digital tools such as analysis and simulation help in aircraft structure certification. Download Now

Close Box

Join Eng-Tips® Today!

Join your peers on the Internet's largest technical engineering professional community.
It's easy to join and it's free.

Here's Why Members Love Eng-Tips Forums:

Register now while it's still free!

Already a member? Close this window and log in.

Join Us             Close